Project Barley, Magna Park for Mclaren Construction

Tiling carried out at one of the largest warehouses in England built in record time.

The new £34 million distribution centre for Waitrose and Gazeley is located on 44.7 acres of land in Milton Keynes.  Incorporated into the distribution centre is a two storey office as well as ‘Goods-in’ and ‘Goods-out’ offices. 

Elite Tiling Limited carried out the Supply & Fix Ceramic Tiling to the Main Office Building Reception floor and Toilet Cores to ground & first floor.  Tiling also carried out to the Goods In & Out Building Reception Floor.

 

Project Barley, Magna Park

 

Project Barley was completed within a tight 32 week programme officially finishing in October 2014, winning a Considerate Constructors Scheme National Site Gold Award 2015.

Main Contractor: McLaren Construction
Client: IDI Gazeley
Architect: Chetswoods
Project completed: October 2014