Handy Cross Leisure Centre Project Progress

Our Tiling Operatives and Site Management team have successfully kept to extremely tight schedules, site management has been crucial in delivering this project on program for the scheduled handover of January 2016 for Willmott Dixon.

Tiling to 50m Main Pool with Moveable Floor

Tiling to 50m Main Pool with Moveable Floor

Tiling to 50m Main Pool with Moveable Floor

Tiling works completed to 50m Main Pool & 20m Learner Pool Tank Floors & Walls.

Finger Grips to Main Pool surround in progress ready for Screeding application.

Pool Surrounds to be Tiled in the Learner Pool.

Mastic Works completed by GRS ONE Ltd.

Feature Wall to wet change area completed.

Tiling to wet change Walls in progress & Dry Change Floors & Walls also in progress.

Tiling to the first floor Steam Room & Sauna Areas are completed with the WC’s, changing areas & showers  on-going .