Riverside Ice and Leisure – Tiling Works Underway As Councillor Lays First Tile

October 26th, 2018


Elite Tiling are pleased to announce that the tiling works are now well underway in the main pool and changing rooms at Riverside Ice and Leisure. The project started in July 2018 and, since then, Elite have successfully completed the Jet Blasting, Screed & Render to the Pool Tanks, along with the Screeding to the Changing Areas.


IMG_1424 (003)

Following completion of the screed and render to the main pool, the pool wall tiling has now begun. To mark this milestone in the project, the first wall tile was ceremoniously laid by a Councillor at Chelmsford Borough Council alongside Directors from Kier.

Main Pool

image12

image22

Changing Rooms

image1

IMG_0542 (003)

image1 (003)

Works are scheduled to continue in the main pool as well as wall and floor tiling starting in the learner and splash pools at the beginning of November.


Anglia Ruskin School of Medicine – Tiling Completed for Willmott Dixon

October 19th, 2018

 logo

Elite Tiling are proud to announce completion of the tiling works at the Anglia Ruskin School of Medicine, Chelmsford campus. It will be Essex’s first medical school, training the doctors of the future. Construction began in May 2017 on the new £20 million building which features state-of-the-art skills facilities, specialist teaching space, a lecture theatre, simulation rooms and an anatomy suite. The medical school will complement the existing facilities, such as the £3.4 million SuperLab.

Elite Tiling had the pleasure of working alongside the team at Willmott Dixon on this project, with whom we are proud to be a Category A Supply Chain member.

Tiling works included a 300m2 Reception in 600 x 600 tiles along with tiling to 50nr stair treads and risers from the ground up to the second floor including nosing edges.

Finishes List

Tiles – 600 x 600 Casal Grande Raggio Di Luna

Grout – Mapei Ultracolour 113

Adhesive – Mapei Keraquick Grey

 

Willmott Dixon

Willmott Dixon

Willmott Dixon


 

Elite Tiling Awarded Riverside Ice & Leisure Project for Kier Eastern

June 6th, 2018

We are proud to announce that we have been successful in securing Riverside Ice & Leisure for Kier Eastern in our home town of Chelmsford, Essex.  The project is due to start in July 2018 and Elite will be undertaking the Jet Blasting, Screed & Render to the Pool Tanks, along with the Screeding to the Pool Surrounds & Changing Areas and all Tiling works.

The refurbishment of Riverside Ice & Leisure will include the construction of 3 brand new pools (Main Pool, Leaner Pool & Flume Splash Pool), as well as new changing facilities to both the swimming area and ice rink.  Our works on site will also include floor tiling to the Main Reception area & tiling to the Pool Spectator Seating Stairs.

This project will be carried out using Spectile Wall & Floor Tiles with Ardex Adhesives & Grout.

 

01

 

Project Capella Secured for Kier Construction Major Projects

May 16th, 2018

We are pleased to announce that we have secured Project Capella for Kier Construction Major Projects.  The project is a new build Research Facility for the University of Cambridge; and the tiling works consist of Wall & Floor Tiling to Levels Ground-5th North & South Toilet Cores, Basement Shower Rooms and the Feature Wall Tiling to a Ground Floor Café/Servery.

We commenced work on site in March 2018 and hope to complete in June 2018.

Walls – 316×200 Porcelanosa Jersey Mix, Park Gris, Japan Marine & Blanco Tiles and 300×100 Solus Spirit Series Tiles, fixed with Mapei Adhesive & Grout

Floors – 443×443 Porcelanosa Rodano Acero Tiles, fixed with Mapei Adhesive & Grout.

Elite Tiling Win Gresham Street Fit-out for ISG Construction

May 16th, 2018

Elite Tiling have started works on 55 Gresham Street, London for ISG Construction.  The tiling works within the 11 storey Central London building consists of Toilet Cores from Ground Level – 9th Level & Male/Female Shower and Changing Facilities in the Lower Ground area.

Works commenced in February 2018 and are expected to complete in July 2018.

Walls – 600×600 Caesar Wide Street fixed with Mapei Adhesive & Grout

Floors – 600×300 Johnsons Minerals Flint fixed with Mapei Adhesive & Grout

second-option_revised_website

Works underway at prestigious Alexandra Palace Project

May 16th, 2018

We are proud to announce that Elite Tiling have been successful in securing the Tiling Works to the prestigious East Wing Redevelopment at Alexandra Palace for Willmott Dixon Hitchin.

Formally used as a studio for the BBC, the East Wing is now being refurbished and Elite Tiling will be working within the Public WC Cores and Back of House Office areas.

Wall Tiles – Johnsons Prismatics 200×100 Victorian Green & 200×100 White

Floor Tiles – Johnsons Kerastar 200×200 Granite Natural & Discface.

Works commenced in April 2018 and are expected to end in May/June 2018.

 

Ally Pally July 2017

 

 

 

 

 

Currently onsite with Multiplex Group – One Blackfriars Hotel

November 28th, 2017

Elite Tiling Ltd are delighted to be currently on site at One Blackfriars Hotel for Multiplex Group working to a tight programme delivering a high spec Tiling Package using 1000 x 330mm Porcelanosa  Wall Tiles.

The 5 Storey Boutique Hotel consists of 161 Bedrooms looking over the River Thames, a landmark mixed use development creating a vibrant new place on London’s South Bank.

Over 3000 m2 of  Porcelanosa Wall Tiling and 550 m2 of Porcelanosa  Floor Tiling will be carried out to the Toilets and Hotel En-Suites.

 

Romford Leisure Centre – Pool Tiling Completed

November 24th, 2017

Elite Tiling Ltd are thrilled to announce we are on target to complete our Tiling Program by the 01st December 2017 for Willmott Dixon Construction.

Tiling to the Main Pool & Learner Pool is now complete and both pools are beginning to be filled.

 

Main Pool Tiled Progress 2

Council Leader Roger Ramsey laying the final Pool Tile at Romford Leisure Centre

November 3rd, 2017

Elite Tiling Ltd were proud to have been invited by Willmott Dixon to be part of the Council leader’s planned visit to the Romford Leisure Centre.

Councilor Roger Ramsey placed the last Pool Tile in the new 25m eight-lane Main Pool on Monday 23rd October.The multi-storey £25m complex in Western Road, Romford  is uniquely designed, with the ice rink on the floor above the swimming pool, and is only the third complex of its kind in the UK.

Council Leader Roger Ramsey

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The centre is scheduled to open in April 2018.